The Federal Ministry of Works, on
Monday, said that if the weather and other factors remained friendly,
the nightmare of Lagos residents following the closure of the bridge
would soon end.
Work on one of the eight faulty
expansion joints of the Third Mainland Bridge was on Monday completed
and the bridge partially re-opened to users on the Adeniji-Adele-bound
lane.
Mr Oluwtoyin Obikoya, Lagos State
Controller, Federal Ministry of Works, said that if work on the bridge
was sustained it might result in early delivery by the contractor.
Obikoya, who refused to be specific on
the possible completion date, said that the bridge was closed on Sunday
to enable the casting of one of the demolished expansion joints to be
reconstructed.
He said that the total closure was to
prevent any vibration on the bridge because of vehicular movement in
order to avoid cracks on the newly cast joints.
According to him, cracks on the newly cast joint will result in premature failure of the reconstruction work.
Obikoya said that it may take about two
weeks for the reconstruction of the two joints between the Adeniji-Adele
and Oworonshoki-bound lane.
``The first of the three joints on the
Oworonshoki-Adeniji-Adele lane was completed yesterday. They
(contractors) hope to cast the second one by next week Sunday,” he said
The rehabilitation of the dual carriage
bridge started on July 7, which resulted in the closure of one side to
enable work to go on the three faulty joints.
The controller explained that casting was done on Sundays because of the light traffic usually observed at the weekends.